  • Well #3R - New pump and rehab - Completed May 2024
  • 1,100 feet of line replacement on Tobin Road - Completed May 2024

2023

  • Well #5 - New pump and rehab - Completed May 2023
  • 1,100 feet of line replacement on Thomas Road - Completed July 2023

2022

  • 2,100 feet of line replacement on Thomas Road - Completed August 2022

2021

  • 110 Kamstrup Smart Meters installed - July 2021
  • 30 Kamstrup Smart Meters installed - August 2021
  • Price Plant surface re-coating done - August 2021
  • Remaining Kamstrup Smart Meters installed for entire PFWD residential customers (290 meters) -  Completed November 2021
  • Kamstrup Smart Meters installed for commercial customers - November 2021

2020

  • 1500 feet of line replacement on Thomas Road
  • 2 valve replacements on Tobin Road
  • Valve Replacement on Kurie Road

2019

  • Mathews Rd 1,800 feet of main line replacement

2018

  • 1,258 feet of main line replacement from Black Forest rd. easement to Fagan Rd
  • 7 10 inch valves
  • 150 feet mainline replacement on Teachout Rd
  • 3 10 inch  valves
  • 1 fire hydrant

2017

  • 580 feet mainline replaced
  • 1 fire hydrant
  • two 4 inch valves
  •  1 10 inch valve
  •  Backup Generator installed at price plant for wells 3R and 4

2016

  • Valve replacement two 8 inch and 3 10 inch
  • 3 fire hydrants.

2015

  • 1,220 feet of Mathews rd and Hungate rd. mainline replaced
  • 3 fire hydrants
  • four 10 inch valves

2013

  • Backup Generator installed at squires plant in 2013 for wells #1 and # 5